Pay app kicked back two days before the GC's billing cutoff? Get the rejection reason in writing, fix only the lines it names, and resubmit the undisputed lines this cycle. One contested line on the schedule of values should not push the whole draw 30 days. Split it out, back it up and bill it next cycle.
General info, not legal or financial advice. Your subcontract controls.
Why do GCs reject a subcontractor's pay application?
Most rejections come down to numbers that do not tie out. The GC has to roll your request into its own bill to the owner. Any line it cannot defend upstream gets bounced back to you.
Common reasons subs hear:
- Percent complete is higher than what the superintendent saw on the walk
- Stored materials are billed with no invoice or proof of where they are stored
- A change order is billed before it was approved, or folded into a base line
- Lien waivers are missing or on the wrong form
- Retainage math does not match the subcontract
- Certified payroll is missing on a prevailing wage job
Federal jobs show why the GC is strict. Under FAR 52.232-5, a prime's payment request must itemize amounts by element of work. It must also list each sub's amount for the period, each subcontract total and what each sub was already paid: https://www.acquisition.gov/far/52.232-5 . Your numbers feed that list, so they have to match line for line.
How do you split the undisputed lines from the contested ones?
Treat the rejection as two bills, not one. Ask the GC's project manager to confirm in writing which lines are accepted as submitted. Re-bill those right away at the agreed amounts.
Move each contested amount to its own note with the backup it is missing. That might be photos, a supplier invoice or a signed change order. If the GC disagrees on a percent, ask for a joint walk before the next cutoff and bill the lower number now.
Subs in trade forums complain that GC payments stretch out. Small electrical shops ask how to run pay apps without costly software. A line you can fix in a day should not add a month to that wait.
Worked example
All names and numbers are made up.
Ridgeway Electric has a $240,000 subcontract and billed $48,600 this period. The GC rejected it for two reasons. First, $18,000 of stored switchgear had no supplier invoice. Second, rough-in on a $60,000 line was billed at 60%, while the super saw 50%, a $6,000 gap. Ridgeway resubmitted $24,600 the same day. After 10% retainage of $2,460, it received $22,140 this cycle instead of $0. The switchgear went on next month's application with its invoice attached.
What should a clean pay application package include?
- A continuation sheet whose totals tie exactly to the schedule of values
- Percent complete per line that matches photos or the last walk
- Supplier invoices and storage proof for any stored materials the contract allows you to bill
- Conditional lien waivers on the GC's required form
- Approved change orders as separate lines, each with its signed form
- Retainage at the subcontract rate, plus certified payroll where the job requires it
A short cover email helps too. Include the billing period, the total and one contact for questions. Unsigned extras are the most common hole in a pay app, so get the change in writing before you bill it.
What if the GC still will not say what is wrong?
Ask again in writing. Name the line and the dollar amount you need explained, and ask which date the corrected application must reach them. A dated email trail matters if payment slips again.
On federal work, the government's billing office must return an improper invoice to the prime within 7 days with the reasons, under FAR 52.232-27: https://www.acquisition.gov/far/52.232-27 . That is the prime's clock, not yours. It is still a fair benchmark to ask for. For how fast a federal prime must pay you once it is paid, see FAR 32.112-1 at https://www.acquisition.gov/far/32.112-1 .
While a draw slips a month, payroll does not. For working capital options, see https://mcafax.com/notebook/construction-business-loans . Comparing products? Factoring and an MCA work very differently, as covered in https://mcafax.com/notebook/invoice-factoring-vs-merchant-cash-advance . Then compare paths at https://mcafax.com/notebook/where-to-get-business-funding .